For high-traffic commercial slabs and residential subfloors where rapid turnaround is critical, Mapecem is a hydraulic binder that produces shrinkage-compensated screeds ready for floor coverings in 24 hours. Formulated to control water loss and dry independently of thickness, it achieves a residual moisture level below 2% within a day, allowing the fast installation of timber, vinyl, carpet, and tiles with minimal facility downtime.
What it does
Mapecem is mixed on-site with dry, clean graded aggregates and water to create a high-strength screeding mortar. It develops rapid mechanical strength and high density, allowing tile and stone to be laid after 3 to 4 hours, and resilient or timber floors after 24 hours. The rapid hydration mechanism locks in the mix water, ensuring the screed cures to a highly compact structure that resists alkalies, oils, and solvents under continuous traffic in environments like supermarkets, airports, and hospitals.
Numbers that matter
-
24-hour drying time: Screeds dry to less than 2% residual moisture by weight, preventing moisture-induced adhesive failure or timber cupping when floor coverings are installed the following day.
-
20 to 30-minute open time: A fast working window that requires the mix to be spread, levelled, and tamped immediately after mixing.
-
33 to 47 MPa compressive strength (at 24 hours): High early mechanical strength depending on the mix ratio (350 kg to 450 kg of Mapecem per cubic metre of sand), rising to 47 to 57 MPa after 28 days to support heavy traffic loads.
-
2 to 3 hours to light foot traffic: Allows trade access to the work area to prepare for final levelling or tile installation after only 4 hours.
-
-30°C to +90°C service temperature: Safe for use with embedded underfloor heating systems and in areas exposed to thermal fluctuations.
Where to use it
-
Bonded screeds (10 to 70 mm thick): Applied fresh-on-fresh over a 2 to 3 mm thick slurry of Planicrete SP and Mapecem on prepared, clean concrete.
-
Unbonded and floating screeds (35 to 70 mm thick): Laid over a polyethylene isolating sheet on existing or new slabs, or over compression-resistant insulation boards.
-
Underfloor heating: Suitable for screeds incorporating heating pipes, provided pipes are located at least 25 mm below the surface and covered with reinforcing mesh. Heating systems can be commissioned after 4 days.
-
Patching and repairs: Quick-setting patching of existing screeds in busy public zones subject to continuous foot traffic.
Limitations
- Do not mix Mapecem with other cements, lime, gypsum, or fine sand alone. Use graded aggregates from 0 to 8 mm.
- Do not leave Mapecem dry-mixed with aggregates; add water immediately. Do not exceed 3 to 4 minutes of mixing time, and do not mix in batching plants or transport via concrete mixer trucks due to the fast setting time.
- Do not add water to a prepared mix or remix the mortar after it has begun to set. Do not wet the surface of the laid screed.
- Since Mapecem screeds are exceptionally compact, absorption of water-dispersion adhesives is slow. For timber installations sensitive to moisture, use Ultrabond P990 1K polyurethane adhesive.
- For resilient installations, substrate relative humidity and pH testing must be performed in accordance with AS 1884. If a moisture barrier is required, apply a suitable vapour barrier such as Primer MF or Mapeproof 1K Turbo above the screed.
- To verify dry weight moisture levels, always use a carbide hygrometer. Electronic hygrometers provide only indicative readings.
Installation and detailing
For bonded applications, the concrete substrate must be clean, dry, free of cracks, dust, wax, oil, and traces of gypsum, with existing joints carried through the screed. Mix one 20 kg bag of Mapecem with 80 to 100 kg of graded 0-8 mm gravel and 4 to 8 kg of water depending on aggregate moisture. Incorporate saw cuts to one third of the screed thickness in large bay sizes. If work is interrupted for more than 1 hour, cut the screed perpendicularly and insert steel rods (3 to 6 mm diameter, 20 to 30 cm long) spaced 20 to 30 cm apart into the edge to prevent cracking and differential movement. For bonded screeds over 50 mm thick, or unbonded installations on compressible substrates or over 60 mm thick, incorporate galvanised mesh reinforcement in accordance with AS 3958.1.